We are currently installing meters in the Hythe and Saltwood area. The area has been divided into four phases for works planning purposes. Phase 4:This is the area in which we are currently working. This phase covers all roads from Scanlon’s Bridge west to Palmarsh. Upon completion of the Hythe and Saltwood area we will be going Northwards along the Nailbourne Valley from Lyminge through Elham to Barham before returning to West Hythe and then going down the coastline back towards Dungeness. This page will be updated as we progress providing confirmation of the exact locations to be metered closer to the time. |